Loch Lomond Marina: Construction Phase 4

CONSTRUCTION PHASE 4
March 2017 – September 2017 (Active)

Construction Phase 3

  1. Andy’s Market has been moved from its current location to the new location.
  2. The old Andy’s Market has been demolished and paving removed.
  3. Wicks are to be installed in this area.
  4. Surcharge soil will be moved from its temporary location on the western edge of the property and be placed in the Residential Phase 3 area (same as Step 2 in Phase 1). Additional surcharge soil may be need, requiring additional truckloads of dirt.
  5. The remaining units in Residential Phase 2 will be built.